What the job involved
A condominium owner was re-tiling the bathroom and reworking the kitchen floor level. Both areas needed the existing tiles and bedding removed down to a sound substrate before the new finishes could go down.
Protecting the waterproofing
In the bathroom the waterproofing membrane sits below the screed, and careless hacking breaches it. We worked to the tile bed rather than through it, and inspected the membrane once the tiles were off so the owner knew whether it needed redoing before re-tiling.
Dust and access
Work areas were screened and sheeted, and the crew worked in respirators and eye protection. Debris was bagged in the unit, moved through the service lift at times agreed with building management, and disposed of at a licensed facility.
Scope of works
- check_circle Remove bathroom wall and floor tiles
- check_circle Hack out the tile bed and screed
- check_circle Remove the kitchen floor threshold and screed
- check_circle Inspect and report on the waterproofing membrane
- check_circle Screen work areas and control dust
- check_circle Bag, remove and dispose of all debris